CLIENT
Fay School
DESIGN ENGINEER
Tighe & Bond
PROJECT
Wastewater Treatment Facility
DIVISION
Mechanical Construction
- Constructed new 21,000-gpd membrane bioreactor wastewater treatment facility
- Included 1,800-square-foot masonry building with cast-in-place concrete tanks on first level and vinyl siding veneer and wood trusses with asphalt shingles for the exterior finish
- Installed water reuse system to allow owner to recycle wastewater for use in flushing toilets
- Managed extremely tight job site due to limited access and close proximity to other work
- WhiteWater, Inc. provides contract operations service